California · Davis-Stirling Act

Charging an electric car in a community that would rather you did not.

Two sections, drafted to look like twins. Both void any restriction that effectively prohibits a charging station, both give the association 60 days before silence becomes approval, and both allow "reasonable restrictions" — which they then define in opposite ways.

Sections Civ. Code §§ 4745, 4745.1 Chapter 4, Property Use and Maintenance Reproduced 2 Text verified 2026-10-11

§ 4745(a) reaches any covenant, condition or restriction in a deed or other instrument of transfer, and any provision of a governing document, that effectively prohibits or unreasonably restricts the installation or use of a charging station within an owner's unit or in a designated parking space — a deeded space, a space in the owner's exclusive use common area, or one specifically designated for that owner. Such a provision is void and unenforceable. So is anything else in the documents that conflicts with the section.

§ 4745.1(a) does the same for an EV-dedicated TOU meter — a second electric meter, supplied and installed by the utility, devoted only to vehicle charging and tracking the time of use. It is the thing that lets you buy charging electricity at the overnight rate instead of the household one, and § 4745.1(d) folds the wiring and conduit that connect it to the charger into the protection too, whoever installs them.

"Reasonable restrictions" means two different things

Both sections save provisions that impose reasonable restrictions, and both declare it the policy of the state to promote and encourage charging and remove obstacles to it. Then the definitions part company, and the difference decides most real disputes.

  1. § 4745Restrictions that do not significantly increase the cost of the station, or significantly decrease its efficiency or specified performance — § 4745(b)(2). A test of effects, and a short one. Aesthetics appears nowhere in it.
  2. § 4745.1Restrictions based upon space, aesthetics, structural integrity, and equal access for all homeowners — but the association shall attempt to find a reasonable way to accommodate the request, unless it would have to spend money to do so — § 4745.1(b)(2). A list of permitted grounds, plus a duty to try.

So an architectural committee refusing a charger because the unit will look wrong has reached for a ground its own section does not offer. Refusing a meter on that ground is available to it — and comes attached to an obligation to look for a way to say yes.

Sixty days of silence is an approval

§ 4745(e) and § 4745.1(e), word for word: the application is processed like an application for an architectural modification, and shall not be willfully avoided or delayed. Approval or denial must be in writing. If the application is not denied in writing within 60 days of receipt, it is deemed approved — unless the delay is the result of a reasonable request for more information.

Note what is deemed, because the Act now has two of these clocks and they do different things. Here, silence approves the application outright. On a disaster reconstruction, § 4766(b)(3) says that missing the 30-day deadline makes the application complete — which only starts the clock on the merits. Approval and completeness are not the same prize.

Where the charger goes decides which rules apply

Inside the unit, or in a space that is already yours

This is the case § 4745(a) protects directly. A deeded space, a space in your exclusive use common area, or one specifically designated for you: the restriction is void and the ordinary approval process in subdivision (e) is what remains.

In the common area or exclusive use common area

§ 4745(f)(1) turns the association's discretion into a condition. The owner must get approval first — and the association shall approve if the owner agrees in writing to four things:

  1. Comply with the association's architectural standards for the installation.
  2. Engage a licensed contractor.
  3. Provide a certificate of insurance within 14 days of approval.
  4. Pay both the installation costs and the electricity the station uses.

"Shall approve" is the operative word. Where the owner signs up to all four, approval is not a decision the board gets to make.

In general common area that is not anyone's exclusive use

§ 4745(g) is narrower: a station for one owner's exclusive use may be authorised there only if installing it in that owner's designated parking space is impossible or unreasonably expensive. Where it is, the association enters into a license agreement with the owner for the use of the space, and all of subdivision (f) still applies.

Two provisions open the other direction. § 4745(h) lets the association or the owners install a station in the common area for the use of all members, with terms of use the association develops. And § 4745(i) says in one line that an association may create a new parking space where one did not previously exist to make an installation possible — a power boards are often surprised to learn they have.

No member vote is needed for any of this

Granting a member exclusive use of part of the common area normally takes the affirmative vote of 67 percent of all separate interests. §§ 4600(b)(3)(H) and (I) carve out exactly this case: running utility lines or meters across the common area for a charging station that meets § 4745, and granting a licence under § 4745. See when the members must vote — the charger is one of the places the Act deliberately keeps off the ballot.

The obligations follow the station, not the person

§ 4745(f)(2) binds "the owner and each successive owner". Whoever holds the unit carries the cost of damage to the station, the common area or anyone's separate interest arising from installation, maintenance, repair, removal or replacement; the cost of maintaining, repairing and replacing the station until it is removed, and of restoring the common area afterwards; the electricity; and the duty to disclose the station and these responsibilities to prospective buyers.

The insurance obligation is the one that lapses quietly. § 4745(f)(3) requires a liability policy at all times — whether the station is inside the unit or out in the common area — with the certificate delivered within 14 days of approval and annually thereafter by that owner and each successor. A certificate filed once at installation and never again does not satisfy it.

One exemption, in § 4745(f)(4): no liability policy is required for an existing NEMA standard alternating current power plug. Plugging into the ordinary outlet that is already there is not what this regime is about.

What it costs an association to get this wrong

§ 4745(j): an association that willfully violates the section is liable for actual damages and owes a civil penalty to the applicant of up to $1,000. § 4745(k): in an action by a homeowner to enforce compliance, the prevailing plaintiff is awarded reasonable attorney's fees. § 4745.1(h) and (i) repeat both for the meter.

As with the disaster-rebuild sections, the fee award runs one way. The statute gives it to the prevailing plaintiff, and the plaintiff here is the homeowner.

What changes on 1 January 2027

SB 1267 amends § 4745 in three places, and the direction of travel is towards the association. The full difference is set out under the section text below; in summary it adds use to the list of activities whose damage the owner pays for, makes the installer indemnify or reimburse the association for loss or damage caused by the installation, and declares the Legislature's intent that an association which has complied with the section have civil liability protection for injuries and damages emanating from a charging station it does not own — except where the association was grossly negligent.

Until that date the text above is the text that governs. See SB 1267.

Civil Code § 4745 — the text

Electric Vehicle Charging Stations
Amended by Stats. 2025, Ch. 525, Sec. 1. (SB 770) Effective January 1, 2026.
Amended by SB 1267, in force from 1 January 2027

(a)Any covenant, restriction, or condition contained in any deed, contract, security instrument, or other instrument affecting the transfer or sale of any interest in a common interest development, and any provision of a governing document, as defined in Section 4150, that either effectively prohibits or unreasonably restricts the installation or use of an electric vehicle charging station within an owner’s unit or in a designated parking space, including, but not limited to, a deeded parking space, a parking space in an owner’s exclusive use common area, or a parking space that is specifically designated for use by a particular owner, or is in conflict with this section is void and unenforceable.
(b)(1)This section does not apply to provisions that impose reasonable restrictions on electric vehicle charging stations. However, it is the policy of the state to promote, encourage, and remove obstacles to the use of electric vehicle charging stations.
(b)(2)For purposes of this section, “reasonable restrictions” are restrictions that do not significantly increase the cost of the station or significantly decrease its efficiency or specified performance.
(c)An electric vehicle charging station shall meet applicable health and safety standards and requirements imposed by state and local authorities, and all other applicable zoning, land use, or other ordinances, or land use permits.
(d)For purposes of this section, “electric vehicle charging station” means a station that is designed in compliance with the California Building Standards Code and delivers electricity from a source outside an electric vehicle into one or more electric vehicles. An electric vehicle charging station may include several charge points simultaneously connecting several electric vehicles to the station and any related equipment needed to facilitate charging plug-in electric vehicles.
(e)If approval is required for the installation or use of an electric vehicle charging station, the application for approval shall be processed and approved by the association in the same manner as an application for approval of an architectural modification to the property, and shall not be willfully avoided or delayed. The approval or denial of an application shall be in writing. If an application is not denied in writing within 60 days from the date of receipt of the application, the application shall be deemed approved, unless that delay is the result of a reasonable request for additional information.
(f)If the electric vehicle charging station is to be placed in a common area or an exclusive use common area, as designated in the common interest development’s declaration, the following provisions apply:
(f)(1)The owner first shall obtain approval from the association to install the electric vehicle charging station and the association shall approve the installation if the owner agrees in writing to do all of the following:
(f)(1)(A)Comply with the association’s architectural standards for the installation of the charging station.
(f)(1)(B)Engage a licensed contractor to install the charging station.
(f)(1)(C)Within 14 days of approval, provide a certificate of insurance as required by paragraph (3).
(f)(1)(D)Pay for both the costs associated with the installation of and the electricity usage associated with the charging station.
(f)(2)The owner and each successive owner of the charging station shall be responsible for all of the following:
(f)(2)(A)Costs for damage to the charging station, common area, exclusive use common area, or separate interests resulting from the installation, maintenance, repair, removal, or replacement of the charging station.
(f)(2)(B)Costs for the maintenance, repair, and replacement of the charging station until it has been removed and for the restoration of the common area after removal.
(f)(2)(C)The cost of electricity associated with the charging station.
(f)(2)(D)Disclosing to prospective buyers the existence of any charging station of the owner and the related responsibilities of the owner under this section.
(f)(3)The owner of the charging station, whether located within a separate unit or within the common area or exclusive use common area, shall, at all times, maintain a liability coverage policy. The owner that submitted the application to install the charging station shall provide the association with the corresponding certificate of insurance within 14 days of approval of the application. That owner and each successor owner shall provide the association with the certificate of insurance annually thereafter.
(f)(4)A homeowner shall not be required to maintain a homeowner liability coverage policy for an existing National Electrical Manufacturers Association standard alternating current power plug.
(g)Except as provided in subdivision (h), installation of an electric vehicle charging station for the exclusive use of an owner in a common area, that is not an exclusive use common area, shall be authorized by the association only if installation in the owner’s designated parking space is impossible or unreasonably expensive. In such cases, the association shall enter into a license agreement with the owner for the use of the space in a common area, and the owner shall comply with all of the requirements in subdivision (f).
(h)The association or owners may install an electric vehicle charging station in the common area for the use of all members of the association and, in that case, the association shall develop appropriate terms of use for the charging station.
(i)An association may create a new parking space where one did not previously exist to facilitate the installation of an electric vehicle charging station.
(j)An association that willfully violates this section shall be liable to the applicant or other party for actual damages, and shall pay a civil penalty to the applicant or other party in an amount not to exceed one thousand dollars ($1,000).
(k)In any action by a homeowner requesting to have an electric vehicle charging station installed and seeking to enforce compliance with this section, the prevailing plaintiff shall be awarded reasonable attorney’s fees.

Reproduced verbatim from the California Legislative Counsel's published text and verified word-for-word against a second source (leginfo (Legislative Counsel official bulk code database, LAW_SECTION_TBL) · California Public Law (Public.Law)). California statutes are government edicts and carry no copyright. This is an unofficial reproduction — the official version is published by the Legislative Counsel at leginfo.legislature.ca.gov, and that version governs.
Machine-readable: /data/4745.json — the same text with its subdivision anchors, dates and sources.

Civil Code § 4745.1 — the text

Electric Vehicle Time-of-Use Meters
Added by Stats. 2018, Ch. 376, Sec. 2. (SB 1016) Effective January 1, 2019.

(a)Any covenant, restriction, or condition contained in any deed, contract, security instrument, or other instrument affecting the transfer or sale of any interest in a common interest development, and any provision of a governing document, as defined in Section 4150, that either effectively prohibits or unreasonably restricts the installation or use of an EV-dedicated TOU meter or is in conflict with this section is void and unenforceable.
(b)(1)This section does not apply to provisions that impose reasonable restrictions on the installation of an EV-dedicated TOU meter. However, it is the policy of the state to promote, encourage, and remove obstacles to the effective installation of EV-dedicated TOU meters.
(b)(2)For purposes of this section, “reasonable restrictions” are restrictions based upon space, aesthetics, structural integrity, and equal access to these services for all homeowners, but an association shall attempt to find a reasonable way to accommodate the installation request, unless the association would need to incur an expense.
(c)An EV-dedicated TOU meter shall meet applicable health and safety standards and requirements imposed by state and local authorities, and all other applicable zoning, land use, or other ordinances, or land use permits.
(d)For purposes of this section, an “EV-dedicated TOU meter” means an electric meter supplied and installed by an electric utility, that is separate from, and in addition to, any other electric meter and is devoted exclusively to the charging of electric vehicles, and that tracks the time of use (TOU) when charging occurs. An “EV-dedicated TOU meter” includes any wiring or conduit necessary to connect the electric meter to an electric vehicle charging station, as defined in Section 4745, regardless of whether it is supplied or installed by an electric utility.
(e)If approval is required for the installation or use of an EV-dedicated TOU meter, the application for approval shall be processed and approved by the association in the same manner as an application for approval of an architectural modification to the property, and shall not be willfully avoided or delayed. The approval or denial of an application shall be in writing. If an application is not denied in writing within 60 days from the date of receipt of the application, the application shall be deemed approved, unless that delay is the result of a reasonable request for additional information.
(f)If the EV-dedicated TOU meter is to be placed in a common area or an exclusive use common area, as designated in the common interest development’s declaration, the following provisions apply:
(f)(1)The owner first shall obtain approval from the association to install the EV-dedicated TOU meter and the association shall approve the installation if the owner agrees in writing to do both of the following:
(f)(1)(A)Comply with the association’s architectural standards for the installation of the EV-dedicated TOU meter.
(f)(1)(B)Engage the relevant electric utility to install the EV-dedicated TOU meter and, if necessary, a licensed contractor to install wiring or conduit necessary to connect the electric meter to an EV charging station.
(f)(2)The owner and each successive owner of an EV-dedicated TOU meter shall be responsible for all of the following:
(f)(2)(A)Costs for damage to the EV-dedicated TOU meter, common area, exclusive use common area, or separate interests resulting from the installation, maintenance, repair, removal, or replacement of the EV-dedicated TOU meter.
(f)(2)(B)Costs for the maintenance, repair, and replacement of the EV-dedicated TOU meter until it has been removed and for the restoration of the common area after removal.
(f)(2)(C)Disclosing to prospective buyers the existence of any EV-dedicated TOU meter of the owner and the related responsibilities of the owner under this section.
(g)The association or owners may install an EV-dedicated TOU meter in the common area for the use of all members of the association and, in that case, the association shall develop appropriate terms of use for the EV-dedicated TOU meter.
(h)An association that willfully violates this section shall be liable to the applicant or other party for actual damages, and shall pay a civil penalty to the applicant or other party in an amount not to exceed one thousand dollars ($1,000).
(i)In any action by a homeowner requesting to have an EV-dedicated TOU meter installed and seeking to enforce compliance with this section, the prevailing plaintiff shall be awarded reasonable attorney’s fees.

Reproduced verbatim from the California Legislative Counsel's published text and verified word-for-word against a second source (leginfo (Legislative Counsel official bulk code database, LAW_SECTION_TBL) · California Public Law (Public.Law)). California statutes are government edicts and carry no copyright. This is an unofficial reproduction — the official version is published by the Legislative Counsel at leginfo.legislature.ca.gov, and that version governs.
Machine-readable: /data/4745.1.json — the same text with its subdivision anchors, dates and sources.

Related Architectural review · When the members must vote · SB 1267 Next review quarterly