Rebuilding after a disaster, and the clock the association is now on.

SB 625 added two sections to the Act. The first makes any restriction void to the extent it blocks rebuilding what was there before. The second gives the architectural committee 30 days, then 45, then 60 — and says what happens when it misses them.

Sections Civ. Code §§ 4752, 4766 Act SB 625 · Chapter 548, Statutes of 2025 In force 2026-01-01 Text verified 2026-10-11

Both sections are new law. Neither existed when most associations last revised their architectural guidelines, and neither can be contracted around: § 4752 voids the restriction itself, and § 4766 governs the review whatever the governing documents say about it.

What counts as a disaster

§ 4752(c)(1) gives three routes, and any one of them is enough:

  1. A state of disaster or emergency declared by the federal government.
  2. A state of emergency proclaimed by the Governor under Government Code § 8625.
  3. A local emergency proclaimed by a local governing body or official under Government Code § 8630.

A county proclamation is as good as a federal declaration here. And the section attaches to a structure that was destroyed or damaged in a disaster; it sets no window between the disaster and the rebuilding, and nothing in it limits the disaster to one that happened after 1 January 2026. What the date governs is the review, not the fire.

Substantially similar reconstruction — the five tests

The protection is not a general right to rebuild as you please. It attaches to a defined proposal, and § 4752(c)(3) defines it with five tests, all of which must be met:

  1. The local building code. A proposal counts as compliant if the building permit is deemed approved by the local agency — so a permit the city sat on does not become the association's reason to refuse.
  2. Interior livable square footage ≤ 110 percent of what existed when the structure was damaged or destroyed.
  3. The exterior footprint — either the same location and the same exterior dimensions as before, or setbacks of at least four feet from the side and rear lot lines. Two alternatives, not two requirements.
  4. Height ≤ 110 percent of the previous height, or 100 percent of what the governing documents allow — whichever is greater. An association with a generous height limit cannot use the old roofline to impose a stricter one.
  5. Any objective design standard that was in effect when the structure was destroyed — but only so far as it does not unreasonably increase the cost of building, effectively prohibit it, or extinguish the ability to rebuild at all.

"Objective" is defined, and the definition does the work

§ 4752(c)(2): a standard that involves no personal or subjective judgment and is uniformly verifiable against an external benchmark available and knowable by both the applicant and the association before submittal. A roof pitch in degrees is objective. A rule that the house must suit the character of the neighbourhood, or that the committee must find the design harmonious, is not — and a standard that is not objective is not among the things a rebuild has to satisfy.

The review clock

§ 4766 applies whenever a substantially similar reconstruction goes to a body — which § 4766(h)(1) defines as the association, an architectural review committee, or any similar body, so renaming the committee changes nothing. All the periods are in calendar days, not business days.

  1. 30 daysto decide in writing whether the application is complete — § 4766(b)(1).
  2. 45 daysonce it is complete, to approve it or return a full set of comments with a comprehensive request for revisions — § 4766(c).
  3. 60 daysto give a final written determination on an appeal — § 4766(e)(2).

If the application is incomplete, the body must say so and simultaneously hand over a list of the missing items and a description of how to cure them — not a refusal with the reasons to follow. The owner may then resubmit.

The two provisions with teeth

Silence approves the application

§ 4766(b)(3): if the body does not make a timely determination, the application is deemed to be complete. Not denied, not tolled — complete, which starts the 45-day clock running on the merits. An association that lets the committee go quiet over a summer has made its decision by doing nothing.

The rules freeze on the day you file

The standards that apply are the body's lawfully adopted standards in effect at the time the application was first submitted — § 4766(c)(1) and (c)(2) both say so. And on a resubmission, § 4766(b)(2)(B) bars the body from requiring an item that the documents did not identify as necessary when the application first went in.

Read together, the two close the obvious evasion: adopt a new guideline while the application is pending and apply it to that application. The guideline may be perfectly valid going forward. It does not reach backwards to the file already on the table.

Approval ends it

§ 4766(f)(1): once the body approves, it shall not subject the applicant to any appeals or additional hearings. A neighbour who dislikes the result has no second bite through the committee. The one exception in (f)(2) is the applicant's own departure from what was approved — which is enforcement of the approval, not reopening of it.

Attorney's fees, one way

§ 4752(b) and § 4766(g) each say a court shall award reasonable attorney's fees to the owner or applicant who prevails. Shall, not may — and in one direction only. An association that loses pays; an owner who loses does not. For a board weighing whether to hold out on a rebuild, that asymmetry is the practical fact, not the drafting detail.

Where the appeal goes

§ 4766(e)(1) sends the appeal to the process under § 4765 — the Act's general architectural review section — and adds the 60-day limit on the written determination. So the ordinary rules about who may decide, and the right to be heard before a decision, carry over; what SB 625 adds is a deadline on the answer.

Civil Code § 4752 — the text

Rebuilding After a Disaster — Substantially Similar Reconstruction
Added by Stats. 2025, Ch. 548, Sec. 1. (SB 625) Effective January 1, 2026.
Amended by SB 1433, in force from 1 January 2027

(a)Any covenant, restriction, or condition contained in any deed, contract, security instrument, or other instrument, and any provision of a governing document shall be void and unenforceable to the extent that it prohibits, or includes conditions that have the effect of prohibiting, a substantially similar reconstruction of a residential structure that was destroyed or damaged in a disaster.
(b)A court shall award reasonable attorney’s fees to the owner of a separate interest in a common interest development who prevails in an action to enforce this section.
(c)For purposes of this section, the following definitions apply:
(c)(1)“Disaster” means any of the following:
(c)(1)(A)A state of disaster or emergency declared by the federal government.
(c)(1)(B)A state of emergency proclaimed by the Governor pursuant to Section 8625 of the Government Code.
(c)(1)(C)A local emergency proclaimed by a local governing body or official pursuant to Section 8630 of the Government Code.
(c)(2)“Objective design standard” means a standard that involves no personal or subjective judgment and is uniformly verifiable by reference to an external and uniform benchmark or criterion available and knowable by both the applicant and the association before submittal.
(c)(3)“Substantially similar reconstruction of a residential structure” means a proposal that rebuilds a residential structure on a separate interest located in a common interest development that complies with all of the following:
(c)(3)(A)(i)The local building code.
(c)(3)(A)(ii)For purposes of this subparagraph, a proposal shall be considered to be in compliance with the local building code if the building permit is deemed approved by the local agency with appropriate jurisdiction.
(c)(3)(B)The interior livable square footage of the rebuilt residential structure will not exceed 110 percent of the square footage that existed when the structure was damaged or destroyed.
(c)(3)(C)The exterior footprint of the rebuilt residential structure will meet either of the following:
(c)(3)(C)(i)The rebuilt residential structure will be constructed in the same location and to the same exterior dimensions as the structure that was damaged or destroyed.
(c)(3)(C)(ii)The setbacks for the rebuilt residential structure will be at least four feet from the side and rear lot lines.
(c)(3)(D)The height of the rebuilt residential structure will not exceed 110 percent of the height that existed when the residential structure was damaged or destroyed, or 100 percent of the height allowed by the governing documents of the association in effect at the time the proposal was submitted, whichever is greater.
(c)(3)(E)Any objective design standard in effect at the time the original residential structure was destroyed or damaged in a disaster, provided that the standard does not unreasonably increase the cost to construct, effectively prohibit the construction of, or extinguish the ability to otherwise rebuild, a substantially similar residential structure.

Reproduced verbatim from the California Legislative Counsel's published text and verified word-for-word against a second source (leginfo (Legislative Counsel official bulk code database, LAW_SECTION_TBL) · California Public Law (Public.Law)). California statutes are government edicts and carry no copyright. This is an unofficial reproduction — the official version is published by the Legislative Counsel at leginfo.legislature.ca.gov, and that version governs.
Machine-readable: /data/4752.json — the same text with its subdivision anchors, dates and sources.

Civil Code § 4766 — the text

Architectural Review of a Disaster Reconstruction — Time Limits
Added by Stats. 2025, Ch. 548, Sec. 2. (SB 625) Effective January 1, 2026.

(a)Any covenant, restriction, or condition contained in any deed, contract, security instrument, or other instrument, and any provision of a governing document that subjects a substantially similar reconstruction of a residential structure that was destroyed or damaged in a disaster to review by a body shall be processed and approved in accordance with this section.
(b)(1)The body shall determine whether an application is complete or incomplete and provide written notice of this determination to the applicant no later than 30 calendar days after the body receives the application.
(b)(2)If the body determines that an application is incomplete, the body shall simultaneously provide the applicant with a list of incomplete items and a description of how the application can be made complete.
(b)(2)(A)After receiving a notice that the application is incomplete, an applicant may cure and address the items that are deemed incomplete by the body by resubmitting the application.
(b)(2)(B)In the review of an application resubmitted pursuant to subparagraph (A), the body shall not require the applicant to include an item that was not identified as necessary in covenant, restriction, or condition contained in any deed, contract, security instrument, or other instrument, and any provision of a governing document in effect at the time the application was originally submitted.
(b)(2)(C)(i)If an applicant resubmits an application pursuant to subparagraph (A), the body shall determine whether the additional application has remedied all incomplete items listed in the determination issued pursuant to this paragraph.
(b)(2)(C)(ii)The review and determination of the resubmitted application shall be subject to the timelines and requirements specified in this subdivision.
(b)(3)If the body does not make a timely determination as required by this subdivision, the application or resubmitted application shall be deemed to be complete for the purposes of this section.
(c)Once an application is deemed complete, the body shall conduct any review of the proposed modification to the separate interest, including a substantially similar reconstruction of a residential structure, and do either of the following within 45 calendar days:
(c)(1)If the body determines that the complete application is not compliant with the body’s lawfully adopted standards in effect at the time the application was first submitted, the body shall return in writing a full set of comments to the applicant with a comprehensive request for revisions.
(c)(2)If the body determines that the complete application is compliant with the body’s lawfully adopted standards in effect at the time the application was first submitted, the body shall approve the application and notify the applicant accordingly.
(d)(1)If a body finds that a complete application is noncompliant, the body shall provide the applicant with a list of items that are noncompliant and a description of how the application can be remedied by the applicant within the time limits specified in subdivision (b).
(d)(2)The body shall provide the list and description authorized by paragraph (1) when it transmits its determination to the applicant as required by subdivision (b).
(d)(3)If a body denies an application based on a determination that the application is noncompliant, the applicant may attempt to remedy the application.
(d)(4)If an applicant submits an application pursuant to paragraph (3), the additional application is subject to the timelines of a new application as specified in subdivision (b).
(e)(1)If an application is determined to be incomplete pursuant to subdivision (b) or determined to be noncompliant pursuant to subdivision (d), the body shall provide a process for the applicant to appeal that decision pursuant to Section 4765.
(e)(2)The body shall provide a final written determination on the appeal no later than 60 calendar days after receipt of the applicant’s written appeal.
(f)(1)Once a body approves an application pursuant to this section, the body shall not subject the applicant to any appeals or additional hearings.
(f)(2)The prohibition described in paragraph (1) does not apply to the applicant’s noncompliance with the approved application.
(g)A court shall award reasonable attorney’s fees to the applicant who prevails in an action to enforce this section.
(h)For purposes of this section, the following definitions apply:
(h)(1)“Body” means an association, architectural review committee, or similar body.
(h)(2)“Disaster” has the same meaning as in Section 4752.
(h)(3)“Substantially similar reconstruction of a residential structure” has the same meaning as in Section 4752.

Reproduced verbatim from the California Legislative Counsel's published text and verified word-for-word against a second source (leginfo (Legislative Counsel official bulk code database, LAW_SECTION_TBL) · California Public Law (Public.Law)). California statutes are government edicts and carry no copyright. This is an unofficial reproduction — the official version is published by the Legislative Counsel at leginfo.legislature.ca.gov, and that version governs.
Machine-readable: /data/4766.json — the same text with its subdivision anchors, dates and sources.

Related Architectural review · Governing documents Next review quarterly